Home » Nigerian Cases » Supreme Court » A. Savoia Limited V A. O. Sonubi (2000) LLJR-SC

A. Savoia Limited V A. O. Sonubi (2000) LLJR-SC

A. Savoia Limited V A. O. Sonubi (2000)

LAWGLOBAL HUB Lead Judgment Report

MICHAEL EKUNDAYO OGUNDARE,  J.S.C.

It has always been thought that proceedings by way of arbitration is a quick way to resolution of disputes between contracting parties, when compared with the tardy proceedings of a law court. This case appears to cast some doubt on the truism of this belief.

The parties to this appeal entered into a building contract on 13th April, 1983 by which the Respondent as Contractor, contracted to erect for the Appellant, as Employer two-storey blocks of 6 flats together with out-houses at Plot 7 Parkview Estate Ikoyi Lagos. Before the completion of the building, a dispute arose as a result of which the appellant terminated the contract on 24th March, 1984. The dispute was referred by the parties, to an arbitrator, Dr. T. M. Aluko, an acknowledged civil engineer of no mean repute. Dr. Aluko entered onto the arbitration and after taking evidence from witnesses called by the parties, issued a report containing his award. The report was issued on 8th March, 1985 within a year of the dispute. That is as it should be so far.

The Respondent, as claimant has claimed in the arbitration –

  1. A total sum of N83,410.49 payment for work done by the Respondent from 21st January, to 24th March, 1984;
  2. Payment of retention money of N22,911.00 in respect of all work done by the Respondent; and
  3. Repayment of the sum of N25,000 allegedly loaned to the Appellant by the Respondent.

The Appellant on the other hand counter-claimed for –

  1. Compensation for expenses incurred by him putting right work allegedly done badly by the Respondent;
  2. Damages suffered by him through Respondent’s failure to complete the work satisfactorily and in the 10 months contract period; and
  3. Payment of the sum of N5,000 balance on a N30,000 he gave to Respondent as an advance at the beginning of the contract.

In his award, the arbitrator upheld Respondent’s claim for work done between 21st January and 24th March, 1984 and allowed the sum of N53,105.96 in respect of this claim. On the retention money, he allowed the sum of N22,648.68 instead of N22,911.00 claimed by Respondent.

The arbitrator disallowed the Respondent’s claim for N25,000.00 loan made by it to the Appellant. A total sum of N75,754.64 was made in favour of the Respondent.

On the Appellant’s claims, the arbitrator found that the “unilateral circumstances of that determination (of the contract) must absolve the claimant from liability to refund any expenses incurred by the Respondent in making good these defects”. Consequently, he rejected the Appellant’s claim (1) and (2). He also rejected his claim (3) for N5,000.00. Notwithstanding his rejection of Appellant’s claim (1), the arbitrator awarded him N11,000.00 instead of his claim for N8,095.00 for defective staircase. A further award of N3,000.00 was also made in favour of the Appellant for other defective works; making a total of N14,000.00 made in favour of the Appellant. The final award to the Respondent was put at N61,754.64 to be paid to the latter by the Appellant.

But this was not the end of the matter. For on 19th April, 1985 the Appellant, as applicant, filed an application pursuant to section 12, Arbitration Law, Cap. 10 Laws of Lagos State and Order 73 rule 2 RSC (England), for an order, as subsequently amended, that the award made between the parties to the above-mentioned arbitration by Dr. Timothy Mofolorunso Aluko, the arbitrator therein dated 8th day of March, 1985 be set aside on the following grounds:

  1. That the arbitrator Dr. Timothy Mofolorunsho Aluko misconducted himself by:-
  2. receiving and acting upon contradictory, unreasonable, unwarranted and inconsistent evidence which by law is not admissible and if at all, to which no weight ought to be attached; and
  3. breaching the basic rules of natural justice, equity and good conscience, having applied different yardsticks of justice.

2.That the said award does not deal with, either conclusively, including the issues of delay in completion, bad workmanship and materials.

  1. That the award is bad on the face of it because:-
  2. the principle therein stated as the principle of law according to which the said arbitrator professed to make this award is erroneously stated and applied;
  3. the award is uncertain, contradictory and ambiguous and
  4. the award was improperly procured, the Respondent having;
  5. suppressed vital evidence during the hearing of the arbitration and
  6. tendered forged documents.
  7. That the said arbitrator exceeded his authority by relying on assumptions in displacement of the contract between the parties, and thereby acting on matters not within the terms of reference of the arbitration agreement.
  8. That the arbitrator is biased in his award.

The application was supported by affidavits and a number of documents which included the Report of the Arbitrator (Exh. 3), the Contract documents (exhibit S1), Rules of Procedure for the arbitral proceedings (Exhibit S8) submission of counsel (Exhibit S9) and Evidence of Witnesses (Exhibit S. 10).

After hearing arguments from learned counsel for the parties, the learned trial Judge (Oguntade J. as he then was) in a judgment delivered on 14th October, 1985, found against the Appellant on all issues raised by him except on the issue of N5,000.00 claimed by the Appellant and remitted the “award to the arbitrator to enable him look further into applicant’s claim for N5,000.00 arising from the disputed payment of N25,000.00 and to make such other awards as the justice of the matter deserved.”

The Appellant was dissatisfied with this judgment and appealed to the Court of appeal (Lagos Division) which Court dismissed the appeal and affirmed the judgment of the trial High Court. It, however, made the following consequential order in respect of the disputed sum of N5,000.00:

“In agreement with the learned Judge in the court below, I order that the sum of N5,000.00 being the balance for the loan made to the Respondent by the appellant at the beginning of the contract for the work to be done at Park View Estate, Ikoyi, should be paid to the appellant by the Respondent.”

Being dissatisfied with the judgment of the Court of Appeal, the Appellant has further appealed to this Court upon three grounds of appeal. And in his written brief of argument filed pursuant to the rules of this Court, he formulated two issues as calling for determination in the appeal, that is to say:

  1. Whether the Court of Appeal was right to uphold the judgment of the High Court on the ground that the Arbitrator did not legally misconduct himself by employing his skill, and experience in place of evidence before him
  2. Whether the Court of Appeal should not have set aside the judgment of the High Court on the ground that the learned Judge erred in ruling that the Arbitrator did not contravene the rules of natural justice
See also  Prince J.S. Atolagbe & Anor V. Alhaji Ahmadu Awuni & Ors (1997) LLJR-SC

And at the oral hearing of the appeal, Dr. O. Ajayi, learned counsel for the appellant proffered oral submissions in further elucidation of arguments contained in the brief.

I may observe at this stage that the Respondent neither filed a brief nor took part at the hearing of the appeal.

On Issue (1), it is submitted that an arbitrator must decide on the evidence adduced by the parties and not on his own knowledge and experience acquired in a different capacity. Appellant relied on Owen v. Nicholl (1948) 1 All ER 707. It is also submitted that an arbitrator with expert knowledge or skill could only employ same in the determination of the dispute where the parties consent and authorise the arbitrator to make use of that special knowledge, skill or judgment or “where the parties agree to arbitrate under the rules of a Chamber of Commerce, under which the Arbitrator is appointed for them, and the arbitrator is chosen or appointed because of his knowledge and experience of the trade.” Mediterranean & Eastern Export Co. Ltd. v. Fortress Fabrics Ltd.(1948) 2 All ER 186 is cited in support. It is further submitted that as the arbitrator in the instant case was only a civil engineer and not a quantity surveyor, it could not be said that he was appointed or authorised to make use of his expert knowledge, expertise or experience. It is finally submitted that the arbitrator was in error to use his knowledge and experience in the finding on the value of work done by the Respondent from 21st January to 24th March, 1984 rather than acting on the evidence of the quantity surveyor called by the Appellant. It is contended that by his so doing the arbitrator acted in excess of jurisdiction and his conduct amounted to legal misconduct and his award should be set aside on that ground.

On Issue (2), the main complaint is that the arbitrator refused Appellant’s complaint on the ground that the latter was guilty of wrongful termination of the building contract between the parties. It is submitted that by raising this point suo motu and deciding on it without hearing the parties, the arbitrator acted unfairly against the Appellant by applying different yardsticks in his approach to the case of each party. It is contended that the arbitrator thereby breached the rules of natural justice.

I have carefully considered the submissions of learned counsel for the Appellant. With respect to him, however, I see no merit in the appeal.

True enough, section 12(2) of the Arbitration Law Cap. 10, Laws of Lagos State 1973 applicable to this case, empowered the Court to set aside an award where the arbitrator had misconducted himself or the award had been improperly procured. (See now section 30(1) of the Arbitration and Conciliation Act, Cap 19 Laws of the Federation of Nigeria 1990 incorporating the New York Convention).

What is misconduct is, of course, not defined in the Law nor in the Act. But this Court has, in Taylor Woodrow (Nig.) Ltd. v. Suddentsche Etna-Werk GMBH (1993) 4 NWLR 127, spelt out some conduct that would amount to misconduct within the law. Some of these are:

(1) where the arbitrator fails to comply with the terms, express or implied, of the arbitration agreement;

(2) where, even if the arbitrator complies with the terms of the arbitration agreement, the arbitration makes an award which on grounds of public policy ought not to be enforced;

(3) where the arbitrator has been bribed or corrupted;

(4) technical misconduct, such as where the arbitrator makes a mistake as to the scope of the authority conferred by the agreement of reference. This, however, does not mean that every irregularity of procedure amounts to misconduct;

(5) where the arbitrator or umpire fails to decide all the matters which were referred to him;

(6) where the arbitrator or umpire has breached the rules of natural justice.

(7) If the arbitrator or umpire has failed to act fairly towards both parties, as for example:-

(a) by hearing one party but refusing to hear the other; or

(b) by deciding the case on a point not put by the parties.

Was misconduct, actual or legal, proved against Dr. T.M. Aluko, the arbitrator in this case I rather think not. I think, in his complaint on issue (1), the Appellant got it all wrong.

At the arbitration proceedings one Aiyepola a quantity surveyor gave evidence for the Appellant in respect of the valuation of the work done by the Respondent as at 24th March, 1984 when the contract was determined.

In respect of the evidence of this witness, this is what the arbitrator said:

“Now witness Aiyepola for the Respondent valued the work that had been completed at the time of the determination of the contract as N437,650 of 64.36% of the contract sum. There is thus a gap of N68,691.96. This no doubt will be a source of concern to the Respondent Shonubi. He will however note that his architect has certified and checked all valuations up to the last payment on 21st January, 1984 and those valuations cannot, and are not up for review at this arbitration. What is properly at issue here is whether or not the Claimant should be paid for work between the last payment and the time the contract was determined and what that payment should be. I have already ruled that they were entitled to be paid and that the sum of N53,105.96 be paid to them.”

Earlier in his report the arbitrator had found:

“The Claimant in their Points of Claim asked for payment for work done by them from 21st January, 1984 when they were paid the last certificate and 24th March, 1984 when their contract was determined. Their claim is for materials, plant, wages and payment to a sub-contractor. The Claimant supported their claims with waybills and paysheets.

See also  Daniel Madjemu Vs The State (2001) LLJR-SC

The Claimant would normally be due for another payment from the Respondent about the time the contract was determined by the Respondent but in the event they did not have the opportunity of presenting their valuation for that period before they were sacked. I rule that they are entitled to payment for work done on the project during this period.”

Appellant’s architect had issued certificates for work done by the Respondent up to 21st January, 1984 in the total sum of N430,325. Adding the claim now allowed the Respondent and the retention fee as found by the arbitrator, the total value of work one by the Respondent as at 24th March, 1984 was put at N506,341.96, a sum in excess of Aiyepola’s valuation of N437,650.00 This is the misconduct complained of by the Appellant. He alleged that the arbitrator used his knowledge, expertise and experience in awarding a figure, rather than base his award on the evidence of Aiyepola.

This complaint cannot be correct. The arbitrator’s reasoning is contained in the first passage above. He did not apply his personal knowledge but based his award on the evidence before him. He reasoned very logically that Aiyepola could not be right in his valuation if the Appellant’s architect by his certificates for work done had made Appellant pay to Respondent a total sum of N435,325.00 as at 21st January, 1984. Surely, the Respondent could not have done work to the meagre value of N2,325.00 (the difference between Aiyepola’s valuation and payments already made to the Respondent) in the two months between 21st January and 24th March, 1984. He accepted Respondent’s evidence (with percentage cuts), as he was entitled to do; in preference to Aiyepola’s evidence.

Much has been made of the remark of Ademola JCA who delivered the lead judgment of the Court below. The learned Justice of Appeal remarked thus:

“As to the complaint that the Arbitrator was not appointed because of his previous skill and knowledge in his arbitration, I am of the view that this complaint cannot ground my setting aside the award made by him. The truth of the matter is that the appellant agreed to the appointment proposed by the respondent who nominated a man, highly qualified, professionally and academically in matters of building which is the subject matter of the suit.

I will be more than surprised if in the course of the arbitration such a man as Dr. Aluko would not bring to bear his skill and knowledge and experience to evaluate the amount of work done on the building which is in dispute. In fact it would be the height of professional folly or negligence if he were to refrain from doing so.”

This remark, in my respectful view, is of no moment when one considers what the learned Justice said immediately following this remark. He said:

“In fact doing so within the limit of the evidence put before him is the very reason why he was appointed.

There would have been some substance in the appellant’s contention if the arbitrator learned and skillful, were to go outside the evidence before him and make award using his experience and professional knowledge as a basis for such award. That has not been the case here.”

It is clear that the arbitrator based his findings and award on the evidence before him. The English cases of Owen v. Nicholl (supra) and Mediterrean v. Fortress (supra) are just not apposite to the facts in the present case. Ademola JCA was right when he observed:

“It is simply not correct that the Arbitrator had been capricious or that he had used his judgment or skill to side-track the evidence before him with regard to the valuation of work done by the respondent between 21/1/84 and 23/4/84.”

I agree with the Courts below that a case of misconduct was not proved by the Appellant against the arbitrator. I, therefore, resolve Issue (1) against the Appellant.

On Issue (2), Appellant complained of unfairness by the arbitrator. His complaint is that the arbitrator applied different yardsticks in his consideration of the case of the parties. An example of this was that in the consideration of his case, the arbitrator took up the question of the wrongful termination by him of the contract and decided on it against him without hearing the parties; whereas the point was not put before the arbitrator for adjudication. The Appellant further complained that the arbitrator came to a wrong decision in law on the said point and relied on the Court of Appeal decision in F.H.A. v. Warner & Warner (1986) 5 NWLR (Pt. 42) 473 where it was held that although the employer did not strictly follow the contractual provision for termination of the contract the notice of termination made it clear that the contract was being terminated for the inability of the Contractor to complete the building within the contractual period, and for that reason the contract had effectively been terminated. Appellant also relied on some English authorities which on going through I find not helpful in the determination of this appeal. Warner v. Warner (1993) 6 NWLR (pt. 298) 148 SC does not help the Appellant either.

In considering the claim of the Appellant for damages for failure of the Respondent to complete the contract within the stipulated time of 10 months and for badly done job, the arbitrator commented:

“It is the practice in the construction industry for the owner through his representatives, that is the architect and / or the engineer, to insist on the contractor doing all aspects of a contract in accordance with the specifications both in the quality of materials and in workmanship. Where the contractor does any part of the work not in accordance with these specifications the owner’s representative would normally insist on that part being done again, even if it means demolishing a substantial part of the work by the contractor before doing it again. After the contract is completed and handed over to the owner he normally calls upon the contractor to make good any defects that may surface within the maintenance period. It is only if the contractor fails to do this that the owner is entitled to do the necessary work and reimburse himself from the retention money which accumulated from the periodical interim certificates. It is important however that the contractor be first given the opportunity to make good himself any defects found during the construction or during the maintenance period before the owner makes good such defects himself at the contractor’s expense.

See also  Momodu Oladele & ORS V. The State (1972) LLJR-SC

In the present case the Claimant was not called upon to make good the defects in the staircase, the roof tank, the septic tanks and any other components of the work found defective. Presumably the communication line between the Claimant and the Respondent in their contractor-owner relationship ceased to exist after the Respondent determined the contract by his letter of 24th March, 1984. The unilateral circumstances of that determination must absolve the Claimant from liability to refund any expenses incurred by the Respondent in making good these defects.”

Against this background, he refused Appellant’s claims for special and general damages. After considering another claim of the Appellant for N5,000.00 for money owed and refusing same, the arbitrator proceeded to consider his claims for defective staircase and other defective works (claims he had earlier refused) and awarded N11,000.00 damages as against N8,095.00 claimed for defective staircase and N3000 for other defective works. Clearly the arbitrator could not be right in making an award over and above what was claimed and after that claim had been refused. But the error is in favour of the Appellant. The Respondent who could have complained did not complain. I wonder how the Appellant could now complain of unfairness against him. I may mention that the arbitrator had, after consideration of Respondent’s claim for N25,000.00 refund of loan allegedly made to the Appellant, had refused same. Appellant did not complain of unfairness in this regard. I think the Appellant is just looking for any excuse to avoid the award of the arbitrator.

Contrary to the impression given us by learned counsel for the appellant, the notes of evidence taken at the arbitration proceedings were produced at the High Court and marked Exhibit S. 10. I have gone through Exhibit S. 10 and find no cause to suggest that the arbitrator acted unfairly towards the Appellant in the course of the proceedings before him.

It is submitted on behalf of the Appellant that the arbitrator in finding that the Appellant wrongfully terminated the contract with the Respondent, acted unfairly in raising the issue suo motu and thereby committed a misconduct. I don’t think this submission is right. The question of the termination of the contract was put before the arbitrator by the Appellant when he claimed for damages for Respondent’s failure to complete the building work in 10 months as stipulated in the contract. It is not the Appellant’s case that the arbitrator by finding that the contract was wrongfully terminated by the Appellant, committed an error in law. Rather, it is that (1) the arbitrator was wrong in raising the matter suo motu and (2) the Respondent, having accepted the termination, the Appellant ought not to be deprived of damages for delay and shoddy job.

Either contention cannot be right. I have explained earlier that it was the Appellant by claiming damages for breach of contract, who put the validity of his termination of the contract in issue. I cannot fault the arbitrator for deciding that issue. Although the question of law as to the validity of the termination of the contract was not specifically referred to the arbitrator, it is however material in the decision of the matter referred, in this case by the Appellant. Where a contract is wrongfully terminated by one party, the other party has a choice of either accepting the termination and suing for damages for wrongful termination of the contract or ignore the wrongful termination and perform his own part of the contract and claim thereafter against the wrongful party.

In this case, the Respondent accepted the termination but did not claim for damages for wrongful termination in the arbitration proceedings. His so choosing is no reason for awarding damages to the Appellant for his own wrongful act.

I, therefore, resolve issue(2) also against the Appellant. There is only one point I think I should comment upon even though it is not raised in this appeal. The trial High Court found that the claim of the Appellant for N5,000.00 refund was not resolved by the arbitrator and remitted same to the arbitrator to enable him look further into the Appellant’s claim. There was no appeal against this part of the judgment of the trial Court. The Respondent who should have complained did not complain. The Court of Appeal, however, made an order directing the Respondent to pay the same sum of N5,000.00 to the Appellant. It thus resolves the issue without further reference to the arbitrator.

I think the Court of Appeal acted wrongly in making the order it made. Under sections 11 and 12 of the Arbitration Law of Lagos State, the court’s jurisdiction to interfere with the award of an arbitrator is limited to setting aside an award or remitting a matter to the arbitrator for reconsideration. The Court has no jurisdiction to determine any matter, the subject of an arbitration proceedings.

The trial High Court acted properly in this case in remitting the matter of the Appellant’s claim for N5,000 to the arbitrator for consideration and resolution. With respect to their Lordships of the Court of Appeal, they acted wrongly in making the order that the sum be paid to the Appellant by the Respondent. Their lack of jurisdiction to make the order apart, the issue was not placed before them and they did not hear the parties on it. They ought not to have made the order. As the matter does not arise for consideration in this appeal, I say no more on it. What I have said is for the guidance of the courts in the future.

This appeal fails and it is hereby dismissed by me. As the Respondent took no part in the appeal, I make no order as to costs.


SC. 40/1996

More Posts

Facebook
Twitter
LinkedIn

Leave a Reply

Your email address will not be published. Required fields are marked *

LawGlobal Hub is your innovative global resource of law and more. We ensure easy accessibility to the laws of countries around the world, among others