Home » Nigerian Cases » Supreme Court » Arisons Trading & Eng. Co. Ltd V. The Military Governor Of Ogun State & 2 Ors (2009) LLJR-SC

Arisons Trading & Eng. Co. Ltd V. The Military Governor Of Ogun State & 2 Ors (2009) LLJR-SC

Arisons Trading & Eng. Co. Ltd V. The Military Governor Of Ogun State & 2 Ors (2009)

LAWGLOBAL HUB Lead Judgment Report

T. MUHAMMAD, J.S.C.

The version of the appellant herein, as plaintiff at the Ogun State High Court of Justice, holden at Abeokuta (trial court), is that the plaintiff was a limited liability Company carrying on business, inter alia, as Building and Civil Engineering Contractors based in Abeokuta. In 1981, the plaintiff tendered for and was awarded contract by the defendants, who are respondents, herein, for the construction of 25 kilometers road between Obafemi/Owode Local Government Area of Ogun State. The contract sum was N8,000.00 (Eight Million Naira). The plaintiff was put into possession of the Owode/Obafemi road site by the defendants and work commenced on the said project. The defendants agreed to pay mobilization fees of N1,600,000.00 (One Million, Six Hundred Thousand Naira). Contrary to the terms of the agreement, the mobilization fees were never paid by the defendants. The plaintiff claimed that it suffered damages due to the failure of the defendants to pay the mobilization fees as it had sought and obtained bridging loan in anticipation of the said fees. Subsequently, the defendants made installmental payments periodically, towards settling the mobilization fees. A total sum of N1,975,000.00 was paid. The plaintiff signed an agreement with Messrs YURSEL INSAAT ANONIH SIRUETT of TURSEY which made 40% claim of the project thereof. The plaintiff committed large sums of money to mobilize plants, equipment and machinery. The plaintiff also employed several workers (skilled and unskilled) and qualified engineers both locally and from abroad. The plaintiff commenced work on the Owode/Siwun section when in 1982, the company was directed to shift to Siwun/Obafemi section. The plaintiff incurred some losses in the movement of machines, equipment, plants and site office.

Between 1981 and 1983, a total of eight (8) interim certificates were issued. Three were signed by the Consulting Engineers while five were signed by Ogun State Resident Engineer. The value of each certificate was indicated therein.

When the Military took over in 1983, all contracts, including the project, were suspended by the defendants. A special investigation panel was constituted in 1984 to review and investigate all contracts awarded by the Ogun State Government. During the time, work was suspended by the defendants, all the machines and equipment of the plaintiff were idle, that is from January, 1984 to June, 1986, and the plaintiff incurred substantial losses of revenue it would have earned for hiring out the machines and equipment.

In June 1986, work by the plaintiff again resumed. In August, 1986, dispute again arose in respect of the amount to be paid on work done. The plaintiff had to stop work to clarify the dispute which was clarified in June, 1987. However, the defendants, through a letter dated 30th March, 1988, terminated the contract between them and the plaintiff. Consequent upon the termination of the Contract between the plaintiff and the defendants, the former took out a Writ of Summons from the trial court. In paragraph 48 of its further amended statement of claim, the plaintiff prayed for the following reliefs:

“48 WHEREOF the plaintiff claim(s) as follows:

DECLARATION that defendant’s letter No. 363/307 of 30th March, 1988 purporting to revoke the contract agreement between the plaintiff and the defendants in respect of Owode Road Project is wrongful, improper, null and void.

ORDER for payment of damages for breach of contract are as follows:

(i) Expenses incurred on staff maintenance, Salaries – N305,826.00

(ii) Charges on plants and machineries from January, 1984 to June, 1986 and from August, 1986 – June, 1987 at daily rate as follows:

Bulldozer – N4, 000.00

2 Motor builders at

N2,000.00 each- N4,000.00

Loader – N1, 000.00

Tipper – N800.00

3 Concrete Mixers at N200 – N600.00

Scrapper – N2, 500.00

Roller – N6, 000.00

Water Lancer – N600.00

Caber Vibrator – N300.00

========= – N19,000.00 Per day

Total from January, 1984 to June 1986 and from August, 1986

to June, 1987 at N19, 0000. 00 per day – N23, 853,200.00

(iii) Outstanding payments on certificate 1/1 – N 202,797.76

Interest on outstanding payments at the Rate of 15%

from the date when certificate 9 became due until judgment.

(v) (a) Loss of anticipated profit on N14.8 Million – N3,700,000.00

at 25%

ALTERNATIVELY

(b) Loss of anticipated profit on balance of 55% of

N8 million – N 1,100,000.00

(vi) Interest on judgment debt at the rate of 10%

from the date of judgment until the date of payment”

The defendants, except where they made admissions, denied all material allegations contained in the plaintiff’s amended statement of claim. After full hearing, the trial court granted the principal claims of the plaintiff. It held that the defendants were in breach and awarded damages against them. The trial court, however, refused the claims on charges for plants and machinery which were idle during the period of suspension.

Both parties were dissatisfied with the trial court’s judgment and they appealed to the Court of Appeal, Ibadan, (Court below).The defendants/respondents later abandoned their cross appeal but filed a Respondent’s Notice contending that the findings of the trial court i.e. the plaintiff/appellant was not entitled to a claim for the idleness of its plants and machinery be affirmed on other grounds contained in its Respondent’s notice. The Court below in its judgment, Per Olagunju, JCA, held inter alia:

“The appeal succeeds in parts; the judgment of the lower court in respect of the claim on equipment is affirmed. Appeal on damages is dismissed”

The appellant filed its appeal to this court on the refusal of the court below to grant damages in respect of the equipment and machinery for the suspension period within which they were said to be idle. The appellant filed its brief of argument .The respondents filed their brief of argument. The appellant filed a reply brief in answer to some points raised by the respondents in their brief. Each party adopted and relied on its brief on the hearing date of this appeal.

The appellant formulated five issues for our determination. They are as follows:

i. “whether or not ownership and source of the equipment and machineries (sic) used for the contract in this suit was an issue contested by parties to this case. Grounds 4, 5 and 6

ii. Whether or not the appellant was not denied fair hearing when the court held that the respondents denied the case of the appellant – Ground 3.

iii. Whether from the totality of the evidence before the court, the appellant did not establish that the appellant’s equipment were kept on site while the contract was suspended which would have enabled the appellant to be entitled to judgment in the sum of N23, 853,200.00 claimed as damages for loss of income on her equipment and machineries (sic) that lay idle when the contract was twice suspended. Grounds 7, 8, 9 and 10.

iv. Whether the learned justices of the Court of Appeal can embark on the review of evidence of the parties given at the trial court to the extent of deciding issues which border on the credibility of the witnesses – Ground 1.

v. Whether or not the Respondent’s Notice filed by the respondents in the lower court was appropriate in the circumstances of this case”

On page 8 of the respondent’s brief of argument, the following three issues were formulated for our consideration:

Issue No 1.

“Whether the Court of Appeal rightly interfered with the assessment and evaluation of evidence by the trial court

ISSUE NO.2

Whether there was credible evidence before the court of Appeal in its re-evaluation and re-assessment of the evidence available before the trial court to show that the plaintiff/appellant was entitled to an award of special damages for idleness of its machinery and equipment

ISSUE NO.3

Whether the respondent’s Notice filed in this suit was invalid and without merit”

Issue one formulated by the learned counsel for the appellant is said to have covered grounds 4, 5 and 6 of the grounds of Appeal contained in the Notice of Appeal which is now under consideration.

The claim contained in paragraph 48(4) of the statement of claim is on special damages. Sub-paragraph (f) thereof is on charges on the idle plants and the machinery from January 1984 to June, 1986 and from August, 1986 to June, 1987.It is in the sum of N700,000.00 (Seven Hundred Thousand Naira). The arguments put forward by learned counsel for the appellant are that the learned trial judge declined to grant the claim on plants and machinery because according to him, the evidence of PW 4 required corroboration. He also held that PW1 was a tainted witness. The trial court held further that the appellant had waived its right to claim damages for idleness of its equipment. Learned counsel submitted further that the issues of requiring corroboration for the evidence of PW 4; that PW1 was a tainted witness and whether the appellant had waived its right to claim damages were all resolved by the court below in favour of the appellant. He argued further that in spite of all these, the court below failed to follow the logical conclusion following the setting aside of the reasonings of the trial court which is to award the amount the trial court had found the appellant was entitled to. The court below, instead, embarked on other inquiries and investigations as to the ownership and source of the equipment and machinery. Learned counsel stated that the question relating to ownership and source of the equipment used by the appellant for the project was never an issue contested by the parties either in their pleadings or in evidence at the hearing of the case before the trial court. He submitted that it is trite that parties are bound by their pleadings. Any contention or submission not based on the issues raised and joined in the pleadings would be incompetent and be disregarded by the court. Learned counsel cited the case of IYARE V. OMOROGUN (1976) 7 – 10 SC. 165; LANA V. UNIBADAN (1987) 4 NWRL (pt.64) P. 245.

In his submission on the same issue, which is contained in issue NO.2 of the respondent’s issues, the learned counsel for the respondents stated that the general principle of law which is so trite is that not only must special damages be specifically pleaded, they must also be strictly proved with credible evidence. Without such proof, no special damages can be awarded. Learned counsel cited several authorities which included inter alia OSUJI V. ISIOCHA (1989) 3 NWLR (Pt. 111) 627; ALHAJI OTARU & SONS LTD. V. IDRIS (1999) 6 NWLR (Pt.606) 330. Learned counsel submitted further that the Court of Appeal in view of the discrepancies it found in the evidence before the trial court, had little choice but to hold that the appellant had not made out its claim for damages for non-use or idleness of its, machinery and equipment. He submitted further that the appellant had not put credible evidence before the trial court to entitle it to the damages for hire.

In the reply brief filed on behalf of the appellant, learned counsel for the appellant submitted that issue No.2 formulated by the respondents was not distilled from grounds 5, 6, 7, 8, 9 and 10 as claimed by the respondents. The issue has no legs to stand on. It is incompetent and liable to be struck out. In an alternative submission, the learned counsel for the appellant stated that if the issue is found to evolve from grounds 5, 6, 7, 8, 9 and 10, then the argument canvassed by the respondents are utterly misleading and misdirected. The case cited by the respondents, that is, SOMMER V. FEDERAL HOUSING AUTHORITY (1992)1 NWLR (Pt. 219) 548 at page 562 is completely different from the present case. Learned counsel submitted that the claim for special damages by the appellant on account of the idleness of the machinery was not misplaced at all and that there is no known rule that stipulates that the contractor must be the owner of all machinery or equipment used in the execution of any contract before he/it can claim damages that may arise therefrom. The comparison made by the respondent’s counsel between the claim for damages in this appeal and for trespass in land is most inappropriate and misconceived.

See also  Yisa Abdulrahman V. The State (2018) LLJR-SC

I will take up this issue together with appellant’s issue no. [iii] as they are inter-related though covered by different grounds. Under these issues, but particularly issue No.3, the main bone of contention is the claim by the appellant’s loss of income for non-use or idleness of its machinery and equipment during the periods of suspension of the contract (that is from January, 1984 to June, 1986 and from August, 1986 to June, 1987). The total sum claimed was N23, 853,200.00. Two views were expressed by the learned trial judge. In his first view, the learned trial judge found that the plaintiff had not proved the item of claim satisfactorily and he dismissed the claim. In his alternative view, the learned trial judge dismissed the claim on that item as well, in spite of all speculations. The discussion by the court below on these issues is interesting. It is fairly lengthy but I found it pertinent to reproduce it herein below as follows:

“On the equipment claimed to be at the contract site at the material time, the learned counsel juxtaposed the list of the equipment of claim in sub-paragraph 28(a) of the statement of claim with the list of the equipment on page 10 of Exhibit ‘A’ which, for the purpose of clarity range as hereunder:

X. The list in sub-paragraph 28(a):

[a] One Fieligun Motor Scrapper

[b] One Bulldozer D7G

[c] Two Motor Graders (one Caterpillar and one Fiat Allis).

[d] One Payloader

[e] One Roller

[f] One Bitumen Sprayer

[g] Two Water Tankers

[h] 5 Tipper Lorries

[i] 3 Concrete Mixers

[j] Pocker Vibrator

Y. Page 10 of the Agreement, Exhibit ‘A’:

(Prices excluded)

“1 No. 619 Scrapper

2 No. D8 Bulldozer

1 No. D8 Bulldozer

2 No. 10/12 Ton Roller

8 No. Y cuy Tipper

1 No. 30 Trailer

1 No. 2,000 gallons water Tanker

10 No. Concrete Mixer

4 No. Vibrating Machines

1 No. 12F Grader.”

To ease an understanding of the analysis that follows, let me reiterate that list ‘Y’ above comprises number of equipment and machinery declared by the appellant as owned or possessed by her when the Agreement for execution of the project was being signed by the parties. Thus, to all intents and purposes the equipment and machinery in that list are the property which the appellant declared under the contract as belonging to her and in effect, an integral part of the contract as far as claim under the contract for loss of their use is concerned.

The learned counsel highlighted the discrepancies between five of the ten items on each of the lists. Items (d) and (f) of list ‘X’ (i.e. sub-paragraph 28(a) of the statement of claim), one Pay loader and one bitumen sprayer, are addition to the equipment in list ‘Y’, i. e. the equipment listed in the Agreement. Items (c) and (g) of list ‘X’, two Motor Graders and two Water Tankers, show increase of the equipment by one each over the number enumerated in list ‘Y’ while ‘Fieligun Motor Scrapper’, the first item on list ‘X’, is different from the equipment described as ‘619 Scrapper’, the first item on list ‘Y’. These three items together with the two items noted earlier must represent new equipment acquired by the appellant after signing the contract.

On the discrepancies, no explanation were offered in respect of three item, a Water Tanker by which the number claimed to be owned by the appellant in list ‘Y’ was increased by one, and a payloader and a Bitumen sprayer which are not among the equipment in list ‘Y’. The 4 PW’s explanation that two other equipment, a Michigan scrapper and a Motor Grader, were supplied by the appellant’s Turkish foreign partner is debunked by learned counsel for the respondents who in the Respondent’s Brief of Argument contended that a comparison of Exhibit ‘V’ with Exhibit ‘N’ shows that the Turkish foreign company with which the appellant claimed to be in partnership is a sham.

That leads to the second question posed by learned counsel for the respondents whether, as claimed by her, the appellant in fact, had a foreign partner who contributed equipment and machinery for the execution of the project.

Exhibit ‘V’ is a letter written by the appellant to the respondent’s Tenders Board on 10/4/81 informing the board that the appellant and our Business Associate, Sager and Woener of Munic Germany and Kano, Nigeria are very much privileged to have this opportunity of tendering for the above project”. Exhibit ‘N’ is an agreement executed on 18/5/81 between Stone Construction Company Nigeria Ltd., and Yuksel insaat and Anonim Sirketi, a company registered in Turkey, to form another company to be known as ‘Stone – Yaksel Construction Company Nigeria Ltd.

The 4th PW, deposed, at pages 122-123 of the record, that the appellant was in partnership with a company called Messrs Yuksel Insaat Brisnim Sinket and Turkey, and he produced as evidence of the partnership an agreement, Exhibit ‘N’, to which he deposed that he was a signatory adding ‘the company gave the plaintiff additional equipments’ (sic). There is obviously no nexus between the appellant, Arosons Trading and Engineering Co. Ltd., incorporated on 12/2/80 as per Exhibit ‘D’, and Yuksel Insaat and Anonim Sirketi of Turkey’ which with Stone Construction Company Nigeria Ltd. were to incorporate at an undisclosed date in future another company, Stone – Yuksel Construction Nigeria Ltd., as per the terms stipulated in clause 1 of the Agreement, Exhibit ‘N’.

A close study of Exhibit ‘N’ shows that it is not a partnership agreement between the appellant and any of the two parties to that agreement. Thus, the 4PW’s story about teaming up with a foreign company to execute the contract with the respondents is an illusion which the appellant, Exhibit ‘N’ as evidence of the partnership to which the appellant is a stranger. Indeed, the fact that the Stone Construction Company Nigeria Ltd, on behalf of which the 4 PW signed the agreement, Exhibit ‘N’, is not shown by evidence to have any business connection with the appellant, a limited liability company with its separate identity denoted in law by Exhibit ‘D’, her Certificate of Incorporation, underscores a total lack of any nexus between either of the two parties to that agreement and the appellant.

If as it has been clearly demonstrated, the appellant has no connection with the agreement in Exhibit ‘N’ and if that agreement to which the appellant’s purported partner – Yuksel Insaat Anonim Sirketi Company of Turkey – is a party, is for the formation of a new company by a different name with no link whatsoever with the appellant(sic)the evidence of the 4PW about the appellant’s Turkish foreign partner is a load of hogwash that tears apart at the scams the story of that witness about the participation of any foreign partner in executing the appellant’s contract with the respondents. It is a hare-brained humbug spun to enhance the appellant’s business ego. Equally nonsensical is ‘the tale’ in Exhibit ‘P’, a letter dated 3/4/88, by the appellant’s foreign partner threatening hell and brimstone for her share of profit in the contract. This is, to say the lest,(sic) a pedestrian business ploy steeped in ‘street smarts’.

That brings me to the inscrutable aspect-of foreign participation in the appellant’s business. In Exhibit ‘V’, the appellant wrote to the respondent’s Tenders Board that herself and Sager and Woener of Munic Germany and Kano Nigeria were tendering jointly for the contract with the respondents. But no word was breathed or anything heard afterwards about the enigmatic business associate who without any ado, was superseded by an equally mysterious Turkish foreign partner that resurfaced through an abstruse correspondence, Exhibit ‘P’, to demand for a business bonanza. Indeed, the appellant must have a penchant for foreign – partnership make- believe. It is monstrous!

In any case, that gives the lie to the claim of a foreign partner contributing any equipment to the stock of machinery at the disposal of the respondents. It, however, leaves unaccounted for when and how the appellant acquired the Motor Scrapper by the statement of claim as to a Water Tanker, a Pay loader and a Bitumen Sprayer about which the appellant gives no explanations of when and how they were acquired since they are not among the equipment declared at page 10 of Exhibit ‘A’ to be the stock of the appellant’s machinery at the time of signing the contract.

The five pieces of machinery about which there are no explanations on when and how the appellant acquired them form half of the machinery for which the appellant is claiming damages from the respondents for loss of profit for their non-use. Learned counsel for the respondents submitted that because of failure to prove that the appellant acquired those machineries in fact, he is not entitled to claim for profit for their loss of use. Sommer V. Federal Housing Authority, supra, on which the learned counsel relied, is supportive of his submission with which I am in complete agreement”.

It is clear from the above in-depth-analysis by the court below that:

[i] the plaintiff/appellant laid claim of ownership/possession of -the equipment/machinery in list ‘Y’ when the agreement for execution of the project was being signed.

[ii] there were discrepancies between the items contained by the two lists as portrayed by paragraph 28(a) of the statement of claim and the list on page 10 of the agreement that is Exhibit ‘A’.

[iii] there was no partnership between the appellant and any foreign partner.

[iv] there was no foreign partner that contributed any equipment to the stock of machinery at the disposal of the appellant for the execution of her contract with the respondents.

[v] the appellant could not give explanation on some equipment and machinery as to when and how they were acquired as they did not form part of the appellant’s stock declared at page 10 of Exhibit ‘A’.

Now, a perusal at paragraph 28 of the further amended statement of claim reveals that there were elements of ownership/possession of the equipment and machinery listed thereunder. It stated as follows:

“28 During the time work was suspended by the defendants, all the machines and equipment of the plaintiff were idle and the plaintiff incurred losses of revenue it would have earned for hiring out the machines and equipment.

[a] At the material time, including the time work was suspended, the plaintiff had on site inter alia the following machines and equipment:

[i] One Fieligun Motor scapper

[ii] One Buldozer D7G

[iii] Two Motor Graders (one Caterpillar and fiat Allis)

[iv] One pay loader

[v] One Roller

[vi] One Bitumen Sprayer

[vii] Two water Tankers.

[viii] Five Tipper Lorries

[ix] Three Concrete Mixers

[x] packer Vibrator.

[b} The plaintiff suffered substantial loss due to the idleness of the machineries from (i) January, 1984 to June, 1986 and (ii) from August, 1986 to June, 1987.” (underlining supplied for emphasis).

The court below, in considering the submissions of learned counsel for the respective parties (page 403 of the record), analyzed in details the above claim in relation to the evidence led in relation thereof and came up with the conclusions as contained in the above quoted excerpt from its judgment. I can hardly fault that exercise by the court below. In any event, where there is a failure, a commission or omission by a trial court in relation to an act which the trial ought to do or refrain from doing, the court below is in as good a position as the trial court to do or refrain from doing that act. See: AFRO-CONT. NIG. LTD V. AYANTUYI (1995) 9 NWLR. (pt. 420) 411; FALIYE V. OTAPO (1995) 3 NWLR (381) 1 at page 12.

See also  James Odunayo Vs The State (1972) LLJR-SC

On the remaining equipment and machinery, it is the finding of the court below that there was no proof to entitle the appellant on the special damages claimed. The court below observed:

“The nature of the appellant’s claim as special damages which must, as a rule, be proved strictly makes the submissions of the learned counsel on this point to be compelling.

Particularly apposite on the exposition of the principles on special damages are Messrs Dumez Nig. Ltd. V. P. N. Ogboli, (1972) 1 All NLR (pt. 1) 241, 249-250; Odulaja V. Haddad, (1973 )11 S.C 357,362; West African Examination Council V. Koroye, C1977) 2 S.C 45, 54; Basil V. Fajebe, (1990) 6 NWRL. (Pt. 155) 172, 179-180; Ajikwo V. Ansaldo Nig. Ltd. (1991) 2 NWLR. (pt.173) 359, 373; Aku Nmechu Transport Service Ltd. V. Atoloye, (1993) 6 NWLR. (pt. 293) 233, 257; Guara Securities & Finances Ltd. V. I. T. C. Ltd. (1999) 2 NWLR. (pt.589) 29, 48-49; and Acme Builders Ltd. V. Kaduna State Water Board, (1999) 2 NWLR. (pt. 590) 288, 305-306 and 309.

On the premise of the principles regulating the award of special damages as expounded by those authorities the reproduction by rote of the list of the machinery by the 1 PW and 4 PW bereft of proper identification of each equipment falls far short of what is required to prove special damages. It is trite that special damages must be proved positively from facts which satisfy the court of their truth but not by repeating on oath undigested averments in the statement of claim that are lubricated by various guess-work to lend them semblance of factual authenticity: see Ntiti V. Afatsao (1970) 2 ALR. Comm. 148, 150-151. The evidence by the appellant has failed to establish the company’s possession or ownership of the other five equipment.”

I am in complete agreement with the court below. Not only must special damages be specifically pleaded they must be strictly proved by the plaintiff. See: OSUJI V. ISIOCHA (1989) 3 NWLR (pt. 111) 623; OTARU & SONS LTD. V. IDRIS (1999) 6 NWLR (pt.606) 330; ATTORNEY GENERAL OYO STATE V. FAIRLAKES HOTEL NO.2 (Supra). They are those pecuniary losses actually suffered up to the date of the trial, such as loss of earnings. The requirement of the law in relation to such damages is that it must be pleaded and proved. It is not a matter of hypothetical exercise nor can it be left to conjuncture. If the appellant was to realize, anything from the special damages claimed, it should, have gone further to lead evidence on those who made inquiries to hire each item of the equipment/machinery. It should have also led evidence in proof of loss of interest from the capital which lay idle, depreciation and maintenance. Further, there was no evidence of how old or new the machinery or equipment were and whether they could really endure work for the 1248 days claimed. Thus, the appellant failed to prove any facts on which the special damages could be estimated. Issues 1 and 3 must fail and are hereby resolved against the appellant.

On the appellant’s second issue, that is, denial of fair hearing, learned counsel for the appellant submitted that in paragraph 28, 28(a), 28(b), 28(c) and claim 2(ii) of the statement of claim, the appellant highlighted the machines and equipment and made a claim of what it lost during the suspension of the contract. The defence did not join any issue on this but made a general traverse by denying it. It is settled law, he argued, that general traverse is insufficient denial of specific allegations but only constitutes admission. The trial court took it upon itself to wade through the records of proceedings and found an answer to the appellant’s issue on this point. Learned counsel faulted the court below’s application of the principle which allows a defective brief to be heard on the merit to be used to make a case for a party and that approach by the lower court had led to a great injustice to the appellant as the appellant had no opportunity to address the answers or case which the court made for the respondents. Learned counsel submitted further that where a respondent failed to respond to an issue raised by the appellant in its brief, the respondent is deemed to have admitted that issue. Some of the respondents in the appeal did not file respondents’ brief even though records show that allegations were made against them and they were served with hearing notices. All these, according to the learned counsel for the appellant occasioned injustice and the appellant was denied fair hearing. Learned counsel cited and relied on the cases of ADONRI V. OSAGIE (1994) SCNJ (pt.11) 192 at 194;OJE V. BABALOLA (1991) SCNJ 110.

The submission of learned counsel for the respondents is that the learned counsel for the appellant was misconceived of the issue of non-joinder of issues between the appellant and the respondents on the issue of idleness of appellant’s machinery and equipment. Learned counsel for the respondents pointed out that appellant’s learned counsel referred to certain paragraphs – 6.04, 6.05 and 6.06 in the brief he filed at the lower court and also at page 12 of his brief, paragraph 5.03 where he stated the findings of the lower court in respect of this issue. Respondents’ learned counsel argued that the issue not pleaded as stated by the court below was on waiver. He argued further that the defendants indeed joined issues with the appellant on damages for idleness or non-use of the machinery and equipment. He urged this court to discountenance this issue.

The allegation posed by appellant’s issue No.2 is on denial of fair hearing to the appellant in the sense that the appellant was not afforded an opportunity to answer the case, which appellant said was made by the court below for the respondents that a court must accommodate a deflective or inelegant brief of argument by a party which must not be allowed to operate any hindrance to an

appeal being heard on the merits.

I think, a convenient point of starting the consideration of this issue is to have recourse to the pleadings, the evidence and the findings of the trial court. The plaintiff pleaded in paragraph 28 of his further amended statement of claim as follows:

“28 During the time work was suspended by the defendants, all the machines and equipment of the plaintiff were idle and the plaintiff incurred losses of revenue it would have earned for hiring out the machines and equipment.

[a] At the material time, including the time work was suspended, the plaintiff had on site inter alia the following machines and equipment:

[i] One Fieligun Motor scapper

[ii] One Buldozer D7G

[iii] Two Motor Graders(one Caterpillar and fiat Allis)

[iv] One pay loader

[v] One Roller

[vi] One Bitumen Sprayer

[vii] Two water Tankers

[viii] Five Tipper Lames

[ix] Three Concrete Mixers

[x] packer Vibrator.

[b] The plaintiff suffered substantial loss due to the idleness of the machinery from (i) January, 1984 to June, 1986 and (ii) from August, 1986 to June, 1987.”

Equipment Rental Rates

Per Day

1 Michigan motor N2, 500.00

Scaooer

2 Buldozer N4, 000.00

3 Motor Graders N4, 000.00

(N2,000 x 2)

4 Pay Loaders N1,000.00

5 Roller 600.00

6 Bitumen Sprayer 800.00

7 Water Tankers N1, 200.00

(1600 x 2)

8 Tipper Lories N4, 000.00

(N800 x 5)

9 Concrete mixers 600.00

(N200 x 3)

  1. Pocker Vibrator 300.00

Total N19, 000.00

(c) After making allowances for overhead, repairs and maintenance of irregular booking etc, the plaintiff lost an estimated N700,000.00 (Seven Hundred Thousand Naira) for idleness of machineries during the suspension of work for which the defendants were responsible.”

Claim 2(ii) of the further Amended statement of claim states as follows:

“2. ORDER for payment of damages for breach of contract are as follows:

{i} Expenses incurred on staff maintenance N305,826.00

{ii} Charges on plants and machineries (sic) from January, 1984 to June, 1986 and from August, 1986 to June, 1987 at daily rate are as follows:

Bulldozer – N4,000.00

2 Motor builders

at N2, 000.00 each – N4,000.00

Loader – N2,000.00

Tipper – N800.00

3 Concrete Mixers at N200-N600.00

Scrapper – N2,500.00

Roller – N6,000.00

Water Lancer – N600.00

Caber Vibrator – N300.00

=========

N19, 800.00P.D

Total from January, 1984 to June, 1986 and from August, 1986 to June, 1987 at N19, 600 per day N23, 853,200.00”

In their joint statement of defence, the 1st, 2nd and 3rd defendants averred as follows:

“SAVE AND EXCEPT as are hereinafter expressly admitted, the defendants deny each and every allegation of fact contained in the plaintiff’s statement of claim as if each were set out seriatim and specifically denied:………………………

……………………………….

  1. The defendants deny paragraphs 28……..of the plaintiff’s statement of claim and put the plaintiff to the strictest proof thereof.”

The two paragraphs above from the defendants’ statement of defence are what are regarded as ‘general traverse’ in the law of pleadings. A ‘traverse’ simplicita, is a categorical denial in the statement of defence of any fact alleged in the statement of claim. In a traverse, the defendant may deny or refuse to admit the allegation. It is also a general rule, conversely, that a fact not denied is taken to be admitted. Of course, a pleader may by inadvertence fail or omit to deny a fact thereby admit what he should not have admitted. It is in order to salvage such a situation that almost every statement of defence contains what is known as the “GENERAL TRAVERSE”. It is set out as the opening paragraph of the statement of defence but may also come at the end as follows:

“Save as hereunder/hereinbefore (as the case may be) expressly admitted, the defendant denies each and every allegation of fact contained in the statement of claim as though same were herein set out and TRAVERSED SERIATIM’.

In 1976, the Supreme Court held that the denial of a particular paragraph in the statement of claim by means of the general traverse had the same effect as a specific denial of it and that this effect was solely to put the plaintiff to proof of the allegation in that paragraph. See: A.C.E JIMONA LTD. V. NIGERIAN ELECTRICAL CONTRACTING CO. LTD. (1976) 1 All NLR 122. In the case of ATTAH AND ANOR V. NNACHO & ORS. (1965) NMLR 28, which was decided earlier than Jimona’s case (Supra), the same court laid it that by common practice, a general traverse has always been accepted and when employed it puts the opponent to proof of the fact therein stated or alleged. In a much later case, this court, in LEMEZIE V. ONUAGULUCHI (1995) 12 SCNJ, 120, re-stated the position as expounded earlier that a general traverse contained in the statement of defence has been recognized as convenient and permissible. It is a traverse and its effect is that it casts on the plaintiff the burden of proving the obligation denied. It was further held that the general traverse and the whole tenor of the other averments were sufficient traverse. The trial judge made finding on the idleness of appellant’s equipment and machinery during the time work was suspended. This is what he stated:

See also  Professor Aderemi Dada Olutola Vs University Of Ilorin (2004) LLJR-SC

“The issue that is to be determined is the equipment and their numbers on the site during this period in view of the disparity in the list of equipment as given in evidence by the PW4 and those in Exhibit ‘A ‘. This is necessary having regard to the cross examination of the PW4 that he removed or hired out some of the equipment during this period. There is no doubt that there must be some equipment on site to be able to perform to specification but the evidence is not that all the equipments as listed by the PW4 must be on site to be able to perform according to specifications. It must be remembered that the burden is on the plaintiffs to prove this facts and the claim being that of a special damage must be specifically proved. I am in doubt as to the equipment being on site.

This right to claim for these equipment matured from January, 1984 to June, 1986 and from August, 1986 to June, 1987. After this, the plaintiffs continued to deal with the defendants giving an impression that he was not going to insist on this right to claim for the idleness of the equipment. I am of the view that if the contract had not been terminated, the plaintiffs would have not sued to claim for this item of damages. It is therefore, my view that the plaintiffs, in the circumstance, have waved their right to sue to claim for the idleness of the equipment. See: African Petroleum Ltd. V. Owodunni supra.

From the above, the plaintiffs have not proved this item of claim satisfactorily. It fails and it must be dismissed. It is accordingly dismissed.”

He also held later in his alternative view on the same issue as follows:

“In case I am wrong in my conclusion, I shall go further to consider the case on the assumption that the items on the site having been satisfactorily proved…….However, in view of my finding that the evidence that the equipment were on site is not satisfactory, this item of claim must be dismissed. It is accordingly dismissed.”

I think a finding of fact by a court of law is that result or inference arrived by a judge after a careful collation, study and synthesizing of the facts and evidence or otherwise in support of such facts as pleaded by the parties. The learned trial judge in this case could not have come to the conclusion he reached if the pleading or evidence was faulty or unsatisfactory. What the court below did, and rightly in my view, is to expatiate on the circumstances where a general traverse is amplified by other cognate averments in the statement of defence. The court below stated:

“Applying the principle expounded above to the pleadings by the parties, although paragraph 2 of the respondents’ statement of defence is a general traverse of the averments in paragraph 28 of the appellant’s statement of claim and would, if it stands alone, amount to non-denial of the allegations in paragraph 28 of the statement of claim and, in consequence, amounts to admission of the averments therein, nevertheless, subparagraph 26(a) is an amplification of the general traverse in paragraph 2 of the statement of defence; it reads in part thus:

“neither is it”, a reference to the plaintiff, entitled to any charges on plants and machineries (sic) having not maintained any on the contract site during the period of suspension.”

The denial in that passage is strengthened by the general tenor of paragraphs 22, 23(c) and 26 of the statement of defence complaining about the appellant’s lack of equipment and workers to cope with the work and predicates the conclusion that the appellant was in dire shortage of equipment during the subsistence of contract to be able to spare any on the contract site during the period of suspension. It is complemented by paragraph 11 thereof which shows that inability to mobilize equipment and machinery for the execution of the contract had beset the appellant from the beginning of the contract. Those four paragraphs (22, 23, (c), 26 and 11 of the statement of defence reinforced the purport*check of subparagraph 26(a) reproduced in part above. Collectively or severally they expand the general denial in paragraph 2 of the statement of defence of the averments in paragraph 28 of the statement of claim.

Consequently, I am satisfied that notwithstanding the general denial of paragraph 28 of the statement of claim by paragraph 2 of the statement of defence (sic) there other areas of the statement defence where the defence of respondents has been clearly stated and amplified to bring the parties to issue. I am further satisfied that on the state of the pleadings of the parties the respondents did join issue with the appellant on paragraph 28 of the statement of claim within the meaning of the words ‘joining issue”.

I am in complete agreement with the court below in that decision. It has for long been the practice that such general traverse in a statement of defence is always given effect along with the whole tenor of the other averments in the other paragraphs of the statement of defence. Thus, it is not the practice to consider each paragraph of the statement of defence in isolation but in conjunction with other paragraphs so that the issues joined in the pleadings can be properly ascertained. See: UGOCHUKWU V. COOPERATIVE BANK (1996) 7 SCNJ 22 at page 35; PAN ASIAN AFRICAN CO. LTD. V. NICC NIG. LTD. (1982) 9 SC 11. I accordingly resolve issue NO.2 in favour of the respondents. Learned counsel for the appellant made his submission on the 4th issue for determination as follows: that it is most inappropriate for the court below to go into the assessment of the credibility of the witnesses called by the appellant, reviewed them on its own and came into the conclusion that they are not credible and they cannot be believed. Whether a witness is to be believed or not goes to the credibility of the witness and it is only the trial court that saw and heard the witness that can do so and not the Court of Appeal.

Learned counsel for the respondents submitted that the Court of Appeal painstakingly went through the evidence available before the trial court including documentary evidence and found out discrepancies between the list of machinery the appellant cited and the items it was claiming damages for their idleness. It also found from available documentary evidence that the appellant had no foreign partner and thus, none contributed any equipment to the stock of machinery at the disposal of the appellant. The reason for the re-evaluation of the evidence placed before the trial court is better stated by the court below when it said:

“But before I examine the question let me interject for the purpose of clarification that the inquiry projected by the issues canvassed involves probing and, if necessary, interfering with the findings of fact by the court below, an exercise in which the discretion of this court is not unfettered. The general principle is that ordinarily an appellate court will not interfere with the decision of the trial court where so much turns on the credibility or reliability of the witnesses on the rationale that ascription of probative value to such evidence is the primary function of the trial court which saw, heard and assessed the witnesses: See: AKINLOYE V. EYIYOLA, (1968) NMLR. 92, 95; and AWOYALE V. OGUNBIYI (1986) 1 All NLR. (part 1) 371, 377; and AGBABIAKA V. SAIBU, (1988) 7 SCNJ. 305, 318. The court will also not do so for the sheer fancy of substituting its view for the view of the trial court where that court has properly evaluated the evidence and made findings of facts: See: OBODO V. OGBA, (1987) 1 All NLR. (part. 1) p.157, 162-163; and OGBECHIE V. ONOCHIE (1988) 1 NWLR. (part 70) 370, 378.

But an appellate court will disturb the findings of fact by the trial court where such findings are shown to be unreasonable or perverse and not a result of proper exercise of judicial discretion. It will similarly interfere with the decision of the lower court where there is ample evidence and the court failed to evaluate it and make correct findings on the issue as in such a case the appellate court is in a good position as the trial court to make the proper findings: See: SHELL BP PETROLEUM CO. NIG. LTD. V. PERE COLE, (1978) 3 S.C 183, 194; TSOKWA MOTORS NIG. LTD. V. AWONIYI (1999) 1 NWLR. (1999) 1 NWLR. (part 587) 423, 435. An appellate court will also interfere where the findings do not flow from the evidence on which such findings are based: See: ADEMOLAJU V. ADENIPEKUN, (1999) 1 NWLR. (part 587) 440, 455.I am satisfied that within the parameters set by the principles here adumbrated it is proper and permissible for this court to evaluate the evidence before the lower court with a view to seeing where justice of this case lies.”

That of course, is the correct principle of the law where it is found that the trial court has failed in its primary role in evaluating the evidence placed before it by the parties. If an appeal court does not interfere to arrest an apparent miscarriage of justice occasioned by non-evaluation or improper evaluation by a trial court, that will perpetuate injustice in our judicial processes and it is the society that will bear the brunt. In my view, the court below did the right thing. I have no hesitation in dismissing this issue as unmeritorious.

Issue No. 5 is on Respondents’ Notice filed by the respondents praying that the decision of the court below appealed against by the appellant be affirmed on the grounds other than those relied on by the court below.

Let me first and foremost draw attention that a Respondent’s Notice as provided by Order 3 Rule 14(2) of the Court of Appeal Rules is not and does not represent a Notice of Appeal. This is because a respondent’s notice does not contemplate a situation where the applicant will be entitled to ask for a complete reversal in his favour of findings of fact made against him on certain issues contested in the case, though he may have succeeded on other issues. The respondents’ notice filed in this appeal arose from the appeal on hand. I have perused the grounds upon which the respondents’ Notice was predicated. I have carefully perused, compared and contrasted with the reliefs claimed in the appeal and I am contented that the respondents were neither asking for a complete reversal of the findings of fact made against them nor did they ask for anything that would have fundamentally altered the case. See: ADELEKE V. AKINOLUGBADE (1987) 3 NWLR (part 60) 214 at page 216; ATTORNEY GENERAL OYO STATE V. FAIRLAKES HOTELS (No.2) Supra. The respondents’ notice in this matter, in my view, was validly raised. I resolve issue No.5 in favour of the respondents.

In the final result, this appeal lacks merit and it is hereby dismissed. The respondents are entitled to N50,000.00 costs from the appellant.


SC.209/1999

More Posts

Facebook
Twitter
LinkedIn

Leave a Reply

Your email address will not be published. Required fields are marked *

LawGlobal Hub is your innovative global resource of law and more. We ensure easy accessibility to the laws of countries around the world, among others